The Florida Department of Transportation is reporting the following construction alerts associated with the I-4 Ultimate construction project currently in progress in the Orlando Metro area.
New Alert: Intermittent Nightly Lane Closure on SB SR-435/Kirkman Road north of the I-4 interchange: 1 left lane closed. From Sunday 05/17/15 to Wednesday 05/20/15 – 10:00 PM–05:00 AM: Install barrier wall
New Alert: Intermittent Nightly Lane Closure on EB I-4 at the Ramp from Ivanhoe Boulevard to EB I-4: 1 right lane closed. From Monday 05/18/15 to Wednesday 05/20/15 – 09:30 PM–07:00 AM: Install construction entrance
New Alert: Continuous Road Closure on Midiron Drive at Minnesota Avenue: all lanes closed. Beginning Monday 05/18/15: Install drainage
New Alert: Intermittent Daily Lane Closure on NB Formosa Avenue south of Minnesota Avenue: 1 lane closed. From Monday 05/25/15 to Friday 06/05/15 – 07:00 AM–05:30 PM: Install underground pipe
New Alert: Intermittent Nightly Lane Closure on WB I-4 at SR-414/Maitland Boulevard: 1 right lane closed. From Tuesday 05/26/15 to Friday 05/29/15 – 08:30 PM–06:00 AM: Asphalt work
New Alert: Intermittent Nightly Lane Closure on WB I-4 from Robinson Street to Division Avenue: 1 left lane closed. From Tuesday 05/26/15 to Saturday 05/30/15 – 08:30 PM–06:00 AM: Drilling
New Alert: Intermittent Nightly Ramp Closure on the ramp from I-4 EB to Princeton Street: all lanes closed. From Monday 06/01/15 to Thursday 06/04/15 – 10:00 PM–05:00 AM: Temporary widening
Reminder: Intermittent Nightly Lane Closure on NB Tampa Avenue from Long Street to SR-408 ramp to Tampa Avenue: all lanes closed. From Monday 05/18/15 to Friday 05/22/15 – 10:00 PM–06:00 AM: Bridge Work.
Reminder: Intermittent Nightly Lane Closure on WB Long Street from Ramp from NB Tampa Avenue to WB SR-408 to Rio Grande Avenue: 1 right lane closed. From Monday 05/18/15 to Friday 05/22/15 – 10:00 PM–06:00 AM: Debris removal
Reminder: Intermittent Nightly Lane Closure on EB I-4 from US-441/Orange Blossom Trail to Kaley Street: 1 left lane closed. From Monday 05/18/15 to Tuesday 05/19/15 – 10:30 PM–06:30 AM: Pavement drilling
Continuing: Intermittent Nightly Lane Closure on EB I-4 from Kennedy Boulevard to SR-414/Maitland Boulevard: 1 right lane closed. From Sunday 04/12/15 to Friday 05/22/15 – 09:30 PM–07:00 AM: Remove dirt.
Continuing: Intermittent Nightly Ramp Closure on the Ramp from Maitland Boulevard to EB I-4: 1 right lane closed.
From Sunday 04/12/15 to Friday 05/22/15 – 10:00 PM–05:00 AM: Crossing dump trucks
Crossing dump trucks on Ramp C intermittently with the use of flaggers and police officers. Work will be performed Sunday thru Friday nights using a light plant to illuminate the area. We anticipate approximately 3 vehicle crossings per hour, back hauling to the surcharge area. The ramp will be broomed clear after each shift. The crossing will be for moving access material from the surcharge area. This will be on an as needed basis towards the end of this operation if there is surplus material at the surcharge area that needs to be moved to another location
Continuing: Intermittent Daily Lane Closure on WB New Hampshire Street from Gurtler Court to Oakmont Lane: 1 lane closed. From Monday 05/04/15 to Friday 05/29/15 – 09:00 AM–04:00 PM: Staging pile driving equipment
All alerts are for planned activities, which may be cancelled or changed due to weather and other circumstances.